 Preliminary Engineering - Existing Utility Investigation Report - 8-18-2011 (document unavailable)

 Line, Grade and Typical Section Submission - Approved 2-15-2012 (document unavailable)

 Site Characterization Report - Approved 1-24-2012 (document unavailable)

 Pavement Design Report - Approved 3-21-12 (document unavailable)

 Level 1b Categorical Exclusion Evaluation (CEE Document for Environmental Clearance) was Approved by PennDOT on 2-10-2012 (document unavailable)

 Vault Investigation Report - Approved 7-9-2012 (document unavailable)

 Erosion and Sediment Pollution Control - Approval 7-27-2012 (document unavailable)

 Subsurface Investigation Report - Approved 2-9-2012 (document unavailable)

 Penn Avenue Construction Plans - Approved 5-2-2013 (document unavailable)

 Contour Grading and Drainage Plan - Approved 5-2-2013 (document unavailable)

 Traffic Control Plan - Approved 5-2-2013 (document unavailable)

 Signing and Pavement Marking Plan - Approved 5-2-2013 (document unavailable)

 Landscaping Plan - Approved 5-2-2013 (document unavailable)

 Erosion and Sediment Pollution Control Plan - Approved 5-2-2013 (document unavailable)

 Highway Lighting Plan - Approved 5-2-2013 (document unavailable)

 Traffic Signal Plan - Approved 5-2-2013 (document unavailable)

 Cross Sections - Approved 5-2-2013 (document unavailable)